V. 5.2.0.28

Enhancements:

  • Optimization choice to search systematically up the target branch and through the entire resource pool
  • Optimization allocates employees 1st then contractors if there is a Resource Data field with the title “Resource Type” that has at least one value “contractor”
  • Highlight recommendations if Display Candidate from Project Demand

Fixes:

  • Fix multiple selection and Apply issues on the candidates sheet
  • Fix 2 click sort on the Delta column on Effort Forecasts
  • Fix sort on Candidates Row Totals to sort descending on 1st 2 click
  • Fix sort toggle on Delta column on the Effort Forecasts sheet